Information from Harkins for One Ardmore Place:

In the next weeks, Structural Steel frame erection will be wrapping up. There will be three large concrete pours tentatively scheduled to happen sometime in the weeks of 2/12 and 2/19. The timing of these pours will fluctuate based on weather conditions. Communication will be provided as dates are selected. Apartment framing will begin mid-February. This work should not affect traffic outside of the site.

Information from Infrasource for Peco:

Crew 1 (Straubel): Crew will be working on Lancaster Ave, between Booth Lane and Tenmore Rd to splice and pull cables. Monday through Friday Night 7:00 pm to 5:00 am.

  • Flagger Force to direct traffic at each site.
  • There will be minimal traffic disturbance. Most of the work involved will be happening in the manholes, no excavation necessary.
  • NO EXCAVATION OR USE OF HAMMER will be needed.
  • Expected Completion 2/23/2018