Information from Harkins for One Ardmore Place:

In the next weeks, Structural Steel frame erection will be ongoing with deliveries taking place inside the site fence. Apartment framing will begin mid-February. Note that there is a concrete pour scheduled for tomorrow, 1/27 to begin at 8AM and is expected to be complete by 8PM. This work will take place within the site and should not affect the surrounding roads.

Information from Infrasource for Peco:

Crew 1 (Straubel): Crew will be working on Lancaster Ave, between Booth Lane and Tenmore Rd to splice and pull cables. Monday through Friday Night 7:00 pm to 5:00 am.

  • Flagger Force to direct traffic at each site.
  • There will be minimal traffic disturbance. Most of the work involved will be happening in the manholes, no excavation necessary.
  • NO EXCAVATION OR USE OF HAMMER will be needed.
  • Expected Completion 2/23/2018

Restoration Crew (Yard): Crew will be working on spot locations on Monday, 1/29, from 8:00 am to 4:00 pm.

  • Flagger Force to direct traffic at each site.
  • Location 1 at Lancaster Ave and Rittenhouse Place
  • Location 2 at Woodside Ave to repair asphalt patch
  • Expected Completion 1/29/2018