Information from Harkins for One Ardmore Place:

In the next weeks, Structural Steel frame erection will be ongoing. Utility work is tentatively scheduled for overnight of 12/18 – 12/19 in Lancaster Ave at Station Road. This will require a two lane restriction on the north side of Lancaster Ave per the attached sketch from 6PM to 6AM. Paving restoration at this location will be done between Noon and 3PM on Tuesday 12/19 and will also require the same lane restrictions.

Infrasource – Peco

Our 2017 work has been completed. We will resume our work in January of 2018 with electric crews to install cable in the previously installed conduit. Our 2018 schedule will be sent out at a later time prior to our return in the area.