Information from Harkins for One Ardmore Place:

In the next weeks, retail foundation and parking garage structure work will come to completion. Structural Steel will begin week of 12/18. Utility work is tentatively scheduled for overnight of 12/11 – 12/12 in Lancaster Ave at Station Road. This will require a two lane restriction on the north side of Lancaster Ave per the attached sketch from 6PM to 6AM.

Infrasource – Peco

Crew 1 (Zielinski): Crew will be working on Lancaster Ave, at Anderson Ave, to replace a manhole roof. Monday through Thursday Night 7:00 pm to 5:00 am.

  • Flagger Force to direct traffic around the manhole excavation.
  • Manhole condition was marked as unsafe condition and to be replaced ASAP.
  • Crew will be chipping the first night to remove the existing roof. *Notice that there will be noise in the area.
  • Expected Completion 12/07/2017

Crew 2 (Miller): Crew will be working on Lancaster Ave, between Anderson Ave and Cricket Ave to install duct. Monday through Thursday Night 7:00 pm to 5:00 am.

  • Flagger Force to direct traffic for the lane closure.
  • The most north lane in the eastbound direction will have the lane closure.
  • Condition of the existing duct work is poor and unable to get new cable work installed. IFS will replace roughly 120’ of duct work so new cable can be installed.
  • Monday night will be test holing. Tuesday through Thursday will be installing the duct.
  • Expected Completion 12/07/2017

Crew 3 (Straubel): Crew will be working in various locations Monday through Thursday to energize the new cable work that has been installed. The crew will be working with PECO resources throughout the week to complete this work. A map is attached to show you the locations the crews will be present. Those locations are labelled in yellow for your reference.

  • Flagger Force to direct traffic at each site.
  • There will be minimal traffic disturbance. Most of the work involved will be happening in the manholes, no excavation necessary.
  • NO EXCAVATION OR USE OF HAMMER will be needed.
  • Expected Completion 12/08/2017

Abbonizio Paving:

  • Monday – Rittenhouse Place/ Athens Ave – 8:00 AM to 4:00 PM
  • Tuesday – Rittenhouse Place/ Athens Ave – 8:00 AM to 4:00 PM
  • Wednesday – Holland Ave and County Line Ave – 8:00 AM to 4:00 PM
  • Thursday – Holland Ave and County Line Ave – 8:00 AM to 4:00 PM
  • Friday – Holland Ave and County Line Ave – 8:00 AM to 4:00 PM