408, 2017

2 Week Look Ahead (8/4/17)

By |August 4th, 2017|Development, One Ardmore Place|0 Comments

In the next weeks, foundation and parking garage structure work will continue with frequent concrete pours and deliveries that will take place onsite and should not affect traffic. AQUA is expected to complete connections to the water main in Cricket Ave. on Monday 8/7 [...]

2807, 2017

2 Week Look Ahead (7/28/17)

By |July 28th, 2017|Development, One Ardmore Place|0 Comments

In the next weeks, footing and foundation work will continue on the construction site of One Ardmore Place with frequent concrete pours and deliveries that will take place onsite and should not affect traffic. Beginning on 7/31, AQUA will be performing connections to the water main in Cricket Ave. in front of Pucci Manuli [...]

2107, 2017

2 Week Look Ahead (7/21/17)

By |July 21st, 2017|Development, One Ardmore Place|0 Comments

This is another 2 week look ahead from Harkins Builders outlining anticipated construction activities for One Ardmore Place. In the next weeks, footing and foundation work will continue with frequent concrete pours and deliveries that will take place onsite and should not affect traffic [...]

707, 2017

2 Week Look Ahead (7/7/17)

By |July 7th, 2017|Development, One Ardmore Place|0 Comments

This is another 2 week look ahead for One Ardmore Place from Harkins Builders. In the next weeks, footing and foundation work will continue with frequent concrete pours and deliveries that will take place onsite and should not affect traffic [...]

1606, 2017

2 Week Look Ahead (6/16/17)

By |June 16th, 2017|Development, One Ardmore Place|0 Comments

The latest 2 week look ahead shows that Harkins Builders will continue to build concrete footings for the remainder of the month. On Monday, June 19, 2017 [...]

206, 2017

2 Week Look Ahead (6/2/17)

By |June 2nd, 2017|Development, One Ardmore Place|0 Comments

In the next two weeks, Harkins Builders will transition from excavation operations to concrete footings. Expect to see increased activity by dump trucks and concrete trucks [...]

505, 2017

2 Week Look Ahead (5/5/17)

By |May 5th, 2017|Development, One Ardmore Place|0 Comments

Harkins Builders does not project any changes to the 2 week look ahead since last week's update. For the rest of May, construction will be focused on shoring installation and excavation [...]

2904, 2017

2 Week Look Ahead (4/28/17)

By |April 29th, 2017|Development, One Ardmore Place|0 Comments

This 2 week look ahead from Harkins Builders shows that shoring installation and excavation will continue for the coming weeks. Harkins Builders expects increased traffic by dump trucks [...]

2104, 2017

2 Week Look Ahead (4/21/17)

By |April 21st, 2017|Development, One Ardmore Place|0 Comments

The latest 2 week look ahead from Harkins Builders is actually a 6 week look ahead showing anticipated construction activities from now until the end of May. Harkins Builders will primarily be focused on shoring and excavation [...]

1404, 2017

2 Week Look Ahead (4/14/17)

By |April 14th, 2017|Development, One Ardmore Place|0 Comments

According to the latest 2 week look ahead from Harkins Builders, demolition of the Cricket Lot is complete. Harkins Builders will now move on to excavation and shoring installation [...]